Return to: Wrights Hill Fortress Homepage

 RESTORATION WORK:[Ongoing]

 

War Shelter Number One (Mostly completed)

As our main entrance, War Shelter One has been brought up to a good standard, and fitted out with display boards showing photos, articles, and documents from the past and present. While there are still some finishing tasks to be done, restoration here is mostly complete. The floor and internal walls have been replaced, the internal doors have been refitted or replaced. All of the walls, timber and concrete, have been painted. The roof has been covered with a waterproof membrane on the outside.

Engine Room

The Fortress was provided with its own power station. This was located in the Engine Room, along with a workshop for maintenance. At present the room is being repainted and the Engines are being restored. There were two Ruston Hornsby 6VCR units, which drove a pair of 120 kW generators, and a Ruston Hornsby 4VRO unit driving a 22 kW generator. For now we are concentrating on the 4VRO as it is mostly complete, apart from damage by vandals. The larger 6VCR units are missing pistons, connecting rods and many other parts. One activity here is the location of replacement parts.

Water Proofing

Over the years a considerable number of minor leaks have developed. Most are along seams in the concrete tunnel walls where water seeps out. These can be sealed using a proprietary product called Vandex, supplied by a local firm. This is a long term project, due to the enormous scale of the task. Each leak must be cleaned of paint and other materials using a grinder, and then several coats of sealer applied. Then it is simply a case of waiting to see if the leak has been plugged. Fortunately there are very few leaks from which water spurts, as these tend to cause rapid erosion of the concrete. The few that do exist are sealed with another version of Vandex.

Command Post

This tiny room housed the Duty Officer and his assistant. It was originally lined with Pinex over a timber frame. Very little of either lining or frame remains. Convenient from the water proofing point of view, but a severe loss to Architecture. The room would have had an octagonal vertical cross-section, looking in from the door. Once water proofing is complete, the frame will be rebuilt from drawings, and the room rewired. Then a new lining will be installed, followed by the refitting of the one remaining door, and its replacement partner. A display (most likely a diorama) will then be installed.

Repainting Of Tunnels In Number One Area

This has been a large task, not yet fully completed. The tunnels are painted gray from floor to mid way up the wall on each side. From there the walls and roof are white. Ultimately the floors may be returned to their original red. Timber work is gray. Number One Pump Chamber has been painted in the same colour scheme. Number One Magazine will also be painted in a similar way.


What have we restored so far

There is a photo album of more Wrights Hill Fortress images